Zenergi's siteworks expertise delivers Manchester's major tram extension on time.

Discover how strategic project management and technical problem solving extended the UK’s largest tram system to The Trafford Centre.

Read time - 3 minutes
Zenergi’s siteworks expertise delivers Manchester’s major tram extension on time.

What we think

Working with TfGM and Keolis Amey Metrolink on the Trafford Park Line extension tested our ability to deliver complex infrastructure projects under pressure. With good partnership, we delivered. Our end-to-end siteworks approach, from demolition management to metering solutions, is a great example of how we can support major transport developments that connect communities."

John Netherwood

Chief Operations Officer

Zenergi

What Transport for Greater Manchester thought

We would highly recommend Zenergi for their experience – and the wide range of services delivered by their qualified, friendly and efficient team."

Daniel Vaughan

Head of Metrolink

Transport for Greater Manchester

What Keolis Amey Metrolink thought

We can rely on Zenergi for quick and effective responses, no matter what the query is, and would recommend their services to others."

Steven Wolstencroft

Commercial & Procurement Manager

Keolis Amey Metrolink

Transport for Greater Manchester (TfGM) is the local government body responsible for delivering Greater Manchester’s transport strategy and commitments – an immense responsibility for a major city. The Keolis Amey Metrolink tram system is the largest of its kind in the UK, serving 99 stops across eight lines along almost 103km of track, with 120 modern trams catering for more than 34 million journeys annually. When they needed to extend the Trafford Park Line from Manchester city centre to The Trafford Centre, they trusted our siteworks team to deliver this critical infrastructure project.

 

A team effort

From the beginning of this important project, we worked closely with the contractor, MPT, plus Keolis Amey Metrolink, and all stakeholders to deliver an integrated solution. Our collaborative, flexible approach set us up for success when facing tight deadlines, a surprise metering data gap and rescheduled dates due to unforeseen site circumstances. We kept close communication with clients, engineers, contractors and project managers throughout delivery, keeping everyone aligned and informed as we juggled the evolving challenges that you’d expect with any complex project.

Making an impact

Working with the contractor, we managed the complete Siteworks package, including disconnections and site clearance for demolition of seven existing buildings along the proposed route. Our team arranged metering for six new tram stops and coordinated three High Voltage and three Low Voltage substation meters. After we completed the disconnections and demolition works, we facilitated new meter installations and provided Energy Procurement management and metering contracts, securing competitive pricing for the energy requirements. The result? An extended line that improved public transport connections for over 1,300 businesses in Trafford Park, Europe’s largest industrial estate.

Driving Results

When we’re embedded in an assignment, especially complex infrastructure projects, we are always ready to troubleshoot. For example, when we identified High Voltage substation shorting issues that got in the way of meter data retrieval, we acted quickly to resolve the problem. Using historical testing data from previous line openings, we effectively estimated usage and proposed solutions to the meter operator, making sure TfGM and KAM paid for accurate usage rather than zero billing. Throughout the project, our open communication and flexibility helped the team meet all critical path activity deadlines, delivering Manchester’s tram extension with positive outcomes for Trafford Park’s businesses and the wider local community.

7

building demolitions managed

6

new tram stops metered

3

High Voltage substations installed

3

Low Voltage substations installed

The big picture

Our work on the Trafford Park Line extension illustrates the part that siteworks management plays in major infrastructure developments. By combining technical expertise with flexible, collaborative project management, we help transport authorities deliver the connections their communities need."

Dannii McAuley

Group Siteworks Manager

Zenergi

Siteworks

With in-depth knowledge of complex siteworks processes, we can oversee any size of project, from single supply to multiple services, liaising with distribution networks, suppliers, and meter operators. We can resolve complex queries and assist with faults, communications, diagnostic issues and metering roll out projects.
Find out more

Metering and Data Services

Excellent quality data is essential for managing your energy consumption, as well as ensuring you only pay for what you use. We'll help you gain a clearer and more accurate understanding of how much energy your organisation uses and can identify opportunities to make significant energy savings and carbon reductions.
Find out more

Energy Procurement

Energy can be a significant expenditure for any organisation, especially during periods of high market volatility. The type of contract you choose can significantly affect what you’ll pay in the long term and it can be difficult to compare prices when there is an endless product and supplier choice available. Take control of your energy costs by leveraging our real-time market insights and market-leading expertise.
Find out more

Explore the services we delivered for Manchesters tram extension:

Are you interested in exploring how our siteworks expertise can support your infrastructure projects? Have a conversation with one of our team today. We’re trusted to deliver comprehensive project management for large-scale, complex, multi-stakeholder infrastructure projects.

Whether you need siteworks consulting, business energy meter installation, utility management services – or an integrated solution – we can pull together a plan that calls on specialist experience.

Ready to learn more?

Start a conversation to find out more about our siteworks services today.

Contact us

Explore the services we delivered for Manchesters tram extension:

Siteworks

Siteworks

Siteworks

Siteworks

With in-depth knowledge of complex siteworks processes, we can oversee any size of project, from single supply to multiple services, liaising with distribution networks, suppliers, and meter operators. We can resolve complex queries and assist with faults, communications, diagnostic issues and metering roll out projects.
Find out more
Metering and Data Services

Metering and Data Services

Metering and Data Services

Metering and Data Services

Excellent quality data is essential for managing your energy consumption, as well as ensuring you only pay for what you use. We'll help you gain a clearer and more accurate understanding of how much energy your organisation uses and can identify opportunities to make significant energy savings and carbon reductions.
Find out more
Energy Procurement

Energy Procurement

Energy Procurement

Energy Procurement

Energy can be a significant expenditure for any organisation, especially during periods of high market volatility. The type of contract you choose can significantly affect what you’ll pay in the long term and it can be difficult to compare prices when there is an endless product and supplier choice available. Take control of your energy costs by leveraging our real-time market insights and market-leading expertise.
Find out more

Related case studies

How our energy audit identified savings of £50,000 for E-ACT.

How our energy audit identified savings of £50,000 for E-ACT.

Identified energy savings
246,193
kWh
Greener transport: helping Gregory Group meet ambitious goals.

Greener transport: helping Gregory Group meet ambitious goals.

Harry Eaves

Senior Energy Consultant

Zenergi

Discover how our energy audits highlighted £94,955 of annual savings for Aldermore Bank.

Discover how our energy audits highlighted £94,955 of annual savings for Aldermore Bank.

Total carbon saving
172.6
tCO2e
Halving Glenmorangie’s energy costs through strategic building optimisation.

Halving Glenmorangie’s energy costs through strategic building optimisation.

Estimated annual electricity consumption savings
59
%
How we helped Danes Educational Trust unlock £166,000 for carbon reduction.

How we helped Danes Educational Trust secure £166,000 for carbon reduction.

Phase 2 LCSF grant awarded
£
39,000
Leigh Academies Trust: Flexible contract saves over half a million pounds.

Leigh Academies Trust saves £500,000+ through flexible energy purchasing.

Achieved savings: Year one
£
399,311
Partnering with PR Associates to drive compliance and energy efficiency in schools.

Partnering with PR Associates to drive compliance and energy efficiency in schools.

Simon Watts

Partnerships Manager

Zenergi

Shropshire Council: Enabling compliance for over 10 years.

Shropshire Council: Enabling compliance for over 10 years.

Darren Myers

Carbon Compliance Manager

Zenergi